AQSA BUILDING 2MahaRERA P99000030742
by NEW STAR DEVELOPERS AQSA BUILDING 2
21, WALIV VASAI, 401208
Dec 2026
Possession
88.2%
Built
0
Complaints
72
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P99000030742
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2023
- Construction
- 88.2% complete
- Units sold
- 47 of 72
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Planting10%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting90%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started
Building & registration
- RERA registered
- Sept 2021
- Floors
- 10
- Unit mix
- 72 res ยท 0 comm
Buyer community
Connect with other buyers and owners of AQSA BUILDING 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AQSA BUILDING 2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.