Under construction

Joyville Virar Phase 6MahaRERA P99000031256

by Joyville Shapoorji Housing Private Limited

Part and Parcel of 297/2, 298/6, 390B, Virar, Bolinj, 401303

Mar 2025
Possession
72.4%
Built
3
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 72.4%.

Official RERA facts

Registration
P99000031256
Status
New
Stage
Certificate Signed
Possession
March 2025
Construction
72.4% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains95%
Landscaping & Tree Planting85%
Street Lighting85%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting95%
Energy managemcntnot started
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started
Covered Parking75%
Club Housedone

Building & registration

RERA registered
Oct 2021
Floors
25
Architect
EN CON Project Consultant

Buyer community

Connect with other buyers and owners of Joyville Virar Phase 6 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.