PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

OMKAR VASTU COMPLEX

by OMKAR DEVELOPERS

256/1, Palghar, 401102

Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 47.7%.

Official RERA facts

Registration
P99000031421
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
47.7% complete
Units sold
39 of 141

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Oct 2021
Floors
7
Unit mix
141 res ยท 0 comm
Architect
SIDDHIVINAYAK ASSOCIATES

Buyer community

Connect with other buyers and owners of OMKAR VASTU COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OMKAR VASTU COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.