Under construction

DEEP SKYMahaRERA P99000032622

by SAI SHRAM ASSOCIATES

89/1 89/2, GOKHIVARE, 401208

Jun 2027
Possession
43.3%
Built
0
Complaints
96
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Jun 2027 per the RERA filing.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 43.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P99000032622
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2025
Construction
43.3% complete
Units sold
56 of 96

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply35%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2022
Floors
30
Unit mix
90 res ยท 6 comm
Architect
SANAT MEHTA & ASSOCIATES

Buyer community

Connect with other buyers and owners of DEEP SKY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DEEP SKY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.