PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAMAIRA RESIDENCYMahaRERA P99000032801

by AV CRYSTAL SPACE

SURVEY NO 75, VASAI EAST, 401209

Dec 2026
Possession
90.3%
Built
0
Complaints
109
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P99000032801
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
90.3% complete
Units sold
109 of 109

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply35%
Sewerage (Chamber, Lines, Septic Tank , STP)65%
Storm Water Drains85%
Landscaping & Tree Planting50%
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station75%

Building & registration

RERA registered
Jan 2022
Floors
25
Unit mix
109 res ยท 0 comm
Architect
SANAT MEHTA AND ASSOCIATES

Buyer community

Connect with other buyers and owners of SAMAIRA RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAMAIRA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.