TRIPURA RESIDENCYMahaRERA P99000047358

by AMRITA SANDIP BARMERA

SNO 10 HNO 6, Vasai, 401208

Dec 2027
Possession
21.6%
Built
0
Complaints
33
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P99000047358
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2024
Construction
21.6% complete
Units sold
13 of 33

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2022
Floors
8
Unit mix
33 res · 0 comm
Architect
Himesh Gupta And Associates

Buyer community

Connect with other buyers and owners of TRIPURA RESIDENCY — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching TRIPURA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.