Raj ResidenciesMahaRERA P99000047508

by Raj Realty & Infra LLP

Survey No. 161, H No. 3A,3B & 3C, Nallasopara East, 401209

Dec 2025
Possession
90.9%
Built
0
Complaints
82
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 90.9%.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P99000047508
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
90.9% complete
Units sold
32 of 82

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Open Parkingnot started

Building & registration

RERA registered
Nov 2022
Floors
14
Unit mix
82 res · 0 comm
Architect
Prithvi Arch Consultant

Buyer community

Connect with other buyers and owners of Raj Residencies — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Raj Residencies. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.