PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAI DARSHANMahaRERA P99000051324

by SAI SHRADDHA ENTERPRISES

25/1/A PLOT NO 15, PALGHAR, 401404

Dec 2026
Possession
33.9%
Built
0
Complaints
15
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 33.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000051324
Status
New
Stage
Certificate Signed
Possession
December 2026originally March 2025
Construction
33.9% complete
Units sold
0 of 15

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2023
Floors
6
Unit mix
15 res ยท 0 comm
Architect
PARESH MAHADEV GHARAT

Buyer community

Connect with other buyers and owners of SAI DARSHAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI DARSHAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.