Under construction

INFINIA PHASE 1MahaRERA P99000051363

by URBAN LAND SOLUTIONS

9/1/A,9/1/B,9/2,9/5,10/1,12,10/3, TODKAR FARMS, 401404

Dec 2026
Possession
โ€”
Built
0
Complaints
447
Units
Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000051363
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
โ€”
Units sold
60 of 447

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains80%
Landscaping & Tree Planting75%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jun 2023
Architect
Ar SNEHAL BADHE

Buyer community

Connect with other buyers and owners of INFINIA PHASE 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching INFINIA PHASE 1. Real notes from real buyers beat any brochure.

Start a discussion