Under construction

YASHWANT CIRCLEMahaRERA P99000051639

by RAJ ENTERPRISES

Survey No.327/E/1 of Village Virar,Taluka Vasai,Dist Palghar, Virar West, 401303

Dec 2027
Possession
58.7%
Built
0
Complaints
70
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000051639
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
58.7% complete
Units sold
25 of 70

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements25%
Electrical meter room, sub-station, receiving station90%
Open Parkingnot started

Building & registration

RERA registered
Jun 2023
Floors
20
Unit mix
68 res ยท 2 comm
Architect
ABHAY RAUT

Buyer community

Connect with other buyers and owners of YASHWANT CIRCLE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching YASHWANT CIRCLE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.