๐Ÿ—๏ธ
Under construction

Jalaram Eco Homes Phase IMahaRERA P99000052585

by Amar Harshad Upadhyay

Survey No- 177/1, Poman, 401208

Oct 2027
Possession
57.3%
Built
0
Complaints
111
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.

Official RERA facts

Registration
P99000052585
Status
New
Stage
Certificate Signed
Possession
October 2027
Construction
57.3% complete
Units sold
7 of 111

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2023
Floors
8
Unit mix
111 res ยท 0 comm
Architect
Studio Arch

Buyer community

Connect with other buyers and owners of Jalaram Eco Homes Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Jalaram Eco Homes Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.