Under construction

MEGASTONE HORIZONMahaRERA P99000052777

by Megastone Spaces

115, 123/1, TEMBHODE, 401404

Mar 2028
Possession
31.1%
Built
0
Complaints
62
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Mar 2026, now proposed Mar 2028 per the RERA filing.

Official RERA facts

Registration
P99000052777
Status
New
Stage
Certificate Signed
Possession
March 2028originally March 2026
Construction
31.1% complete
Units sold
15 of 62

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2023
Floors
6
Unit mix
62 res ยท 0 comm
Architect
SIDDHIVINAYAK ASSOCIATES

Buyer community

Connect with other buyers and owners of MEGASTONE HORIZON โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.