Under construction

ROOP RAJAT PARK BUILDING NO 7A AND 7BMahaRERA P99000054501

by GAURAV HOME BUILDERS AND DEVELOPERS

157/158.9/168.1/168.2/169.1/169.2, 158/1/1, BETEGAON, 401501

Mar 2027
Possession
81.6%
Built
0
Complaints
56
Units
High risk
  • Possession delayed ~1 yr. Originally promised Jan 2026, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P99000054501
Status
New
Stage
Certificate Signed
Possession
March 2027originally January 2026
Construction
81.6% complete
Units sold
28 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Jan 2024
Floors
8
Unit mix
56 res ยท 0 comm
Architect
PRANAV DESHMUKH

Buyer community

Connect with other buyers and owners of ROOP RAJAT PARK BUILDING NO 7A AND 7B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ROOP RAJAT PARK BUILDING NO 7A AND 7B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.