All RERA projects
๐๏ธ
Under construction
ELITE TOWERMahaRERA P99000055061
Survey No 204, Hissa No. 1 and Survey No 210, Hissa No 2, NILEMORE, 401203
Dec 2027
Possession
34.5%
Built
0
Complaints
218
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P99000055061
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 34.5% complete
- Units sold
- 38 of 218
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Feb 2024
- Floors
- 24
- Unit mix
- 211 res ยท 7 comm
Buyer community
Connect with other buyers and owners of ELITE TOWER โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ELITE TOWER. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.