STUVI RESIDENCY

MahaRERA PR1180002600462High risk

by STUVI REALITY LLP

Goregaon, 400062

Official record
Dec 2029
Possession
Built
0
Complaints
12
Units
High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Agreement deviates from RERA model form. The promoter's allotment letter or agreement for sale is flagged as deviating from MahaRERA's standard proforma — read the actual clauses before signing.
  • Possession delayed ~2 yrs. Originally promised Dec 2027, now proposed Dec 2029 per the RERA filing.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
STUVI REALITY LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
PR1180002600462
Status
New
Stage
Certificate Signed
Possession
December 2029originally December 2027
Construction
Units sold
1 of 12

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 25 Jul 2026).

Litigation record2 cases

  • THE HIGH COURT OF JUDICATURE AT BOMBAYCase WRIT PETITION (L) NO. 12240 of 2025/2025
    The said Writ Petitions were filed by the Petitioners therein challenging the Structural Audit Report dated 15th February, 2025 prepared by Structural Engineer, Mr. Pal Ajay Singh. It is pertinent to note that no reliefs were granted by the Hon’ble Bombay High Court in the favour of the Petitioners in the said Writ Petitions. Thereafter, the Notice bearing No. ACPS/B-55/354/SR/304/AE (B&F)-II dated 16th May, 2025 was issued under section 354 of the Mumbai Municipal Corporation Act, 1888. As a consequence, the legality and validity of the said Notice have attained finality, and the said Old Building was demolished by the BMC. The Promoter has now commenced the redevelopment of the said Property. Accordingly, the pendency of the said Writ Petitions has no bearing on the title or rights of the Promoter, and the reliefs sought under the said Writ Petitions have now become infructuous.
    Status: Closed
  • THE HIGH COURT OF JUDICATURE AT BOMBAYCase WRIT PETITION (L) NO. 12162 of 2025/2025
    The said Writ Petitions were filed by the Petitioners therein challenging the Structural Audit Report dated 15th February, 2025 prepared by Structural Engineer, Mr. Pal Ajay Singh. It is pertinent to note that no reliefs were granted by the Hon’ble Bombay High Court in the favour of the Petitioners in the said Writ Petitions. Thereafter, the Notice bearing No. ACPS/B-55/354/SR/304/AE (B&F)-II dated 16th May, 2025 was issued under section 354 of the Mumbai Municipal Corporation Act, 1888. As a consequence, the legality and validity of the said Notice have attained finality, and the said Old Building was demolished by the BMC. The Promoter has now commenced the redevelopment of the said Property. Accordingly, the pendency of the said Writ Petitions has no bearing on the title or rights of the Promoter, and the reliefs sought under the said Writ Petitions have now become infructuous.
    Status: Closed

The promoter's allotment letter or agreement for sale is flagged as deviating from MahaRERA's standard proforma — read the actual clauses carefully before signing.

Landowner

Mr Shailesh Subhash Juvekar, Mr Rajesh Suresh Juvekar, Mr Ninaad Sharad Juvekar, Smt Sucheta Sharad Juvekar, Sneha Shailesh Juvekar, Tanmay Shailesh Juvekar

Possession extension history

  • EA25062621524Revised to December 2029

    There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.

Building & registration

RERA registered
May 2026
Floors
10 (sanctioned 4)
Unit mix
12 res · 0 comm
Plot / CTS / survey no.
CTS No. 162, 162/1 to 9,
Planning authority
P-25096/2025/(CTS No. 162 And Other)/P/S Ward/PAHADI GOREGAON-W/CC/1/New
Approved layout land
545.2 sq.m
Land for this registration
545.2 sq.m
Recreational open space
0 sq.m
Permissible built-up area
610.04 sq.m
Promoter contact
Rakesh Shah
Registered office
GAONDEVI UTKARSH CHS
Plot boundaries
North
By Road
South
By Plot No.15
East
By ROad No.1
West
By Plot No.19
Parking
12 four-wheeler2 visitor

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • HDFC BANK — 48852
    IFSC HDFC0000398
    SHOP 1-4,MONICA ARCADE,SUBHASH LANE,OFF DAFTARY ROADMALAD EASTMUMBAIMAHARASHTRA400097

Commencement Certificate documents

  • 2503149_FirstCC_signed.pdf

Buyer community

Connect with other buyers and owners of STUVI RESIDENCY — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching STUVI RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 25 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.