All RERA projects

What the RERA filings say about tracked localities

Computed live from official MahaRERA disclosures for every project we track. Every number is verifiable against the project's registration.

3110
under-construction projects tracked
798
pushed possession 6+ months — avg 3.1 yrs
257
complaint records across 31 projects
6
recovery warrants — RERA's strongest action
42%
of 2,98,827 tracked units sold

Longest possession delays

Originally promised vs currently proposed date in the builder's own filing.

Most complaint records

Complaints, misc. applications and recovery warrants disclosed per project. 74 projects have a clean record.

When builders say you'll get keys

Proposed possession year per current RERA filing.

1
2024
1
2025
966
2026
835
2027
600
2028
379
2029
188
2030
84
2031
32
2032
13
2033
6
2034
2
2035
1
2036

Developers by tracked projects

Complaint totals are the sum across each developer's projects here.

DeveloperProjectsComplaintsWarrants
Lodha Developers Limited140
Rare Townships Private Limited80
Hubtown Limited76
Susneh Infrapark Private Limited60
SURAJ ESTATE DEVELOPERS LTD60
SPENTA ENCLAVE PRIVATE LIMITED50
ELEVATED AVENUE REALTY LLP50
Puravankara Limited50
NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED40
SWAYAM REALTORS & TRADERS LLP40
Raheja Universal (Pvt.) Ltd.40
JPV Realtors Private Limited40

Possession due within a year, construction under 50%

Per the builder's own progress disclosure — ask hard questions before booking here.

Source: official MahaRERA portal disclosures, recomputed 18 Jul 2026. Delay = original vs current proposed completion date in the same registration. Complaint counts are disclosed records, not adjudicated outcomes.